Week of Feb. 6, 2023
Accelerated timelines continue as crews are moving quicker than anticipated.
Driveway and sidewalk construction is complete, crews continue to construct retaining curbs and repair related irrigation and landscaping seeding.
The Pedestrian Improvement Project is constructing new driveway approaches, sidewalks, adding crosswalks and updating ADA accessibility ramps to improve safety in your neighborhood.
ADA access accommodations are offered if necessary, please email the outreach team at info@HerbertHooverProject.com with your name, address, phone number, or call the hotline number above.
Work in your area
Stage A: Crews continue ADA ramp improvements, landscaping reconnection and seeding, and other clean-up activities. Driveway reconstruction and sidewalk construction are complete, however, retaining curb work may still take place at specific locations.
Stage B: Crews continue ADA ramp improvements, landscaping reconnection and seeding, and other clean-up activities. Driveway reconstruction and sidewalk construction are complete, however, retaining curb work may still take place at specific locations.
Stage C: Crews continue ADA ramp improvements, landscaping reconnection and seeding, and other clean-up activities. Driveway reconstruction and sidewalk construction are complete, however, retaining curb work may still take place at specific locations.
Stage D: Crews continue ADA ramp improvements, landscaping reconnection and seeding, and other clean-up activities. Driveway reconstruction and sidewalk construction are complete, however, retaining curb work may still take place at specific locations.
Week of January 30, 2023
Accelerated timelines continue as crews are moving quicker than anticipated.
Construction in Stage A and B continue and crews have moved into Stage C ahead of schedule, and will return to the northern section of Stage D.
The Pedestrian Improvement Project is constructing new driveway approaches, sidewalks, adding crosswalks and updating ADA accessibility ramps to improve safety in your neighborhood.
Crews will work on one side then switch to the other side of a street once the initial side is complete. Crews continue with a leapfrog method to reduce inconvenience with resident access restrictions and improve overall efficiency to deliver a high-quality end-product for residents. Thank you for your continued patience.
ADA access accommodations are offered if necessary, please email the outreach team at info@HerbertHooverProject.com with your name, address, phone number, or call the hotline number above.
Work in your area
Stage A: Crews continue ADA ramp improvements, landscaping reconnection and seeding, and other clean-up activities. Driveway reconstruction and sidewalk construction are complete, however, retaining curb work, and fire hydrant relocations may take place. Work on Indio Blvd. is scheduled to continue this week.
Stage B: Crews continue ADA ramp improvements, landscaping reconnection and seeding, and other clean-up activities. Driveway reconstruction and sidewalk construction are complete, however, retaining curb work, and fire hydrant relocations may take place. Work on Monroe St. will continue this week.
Stage C: Crews are working on water meter relocations, utility relocations, saw cutting work and other construction activities. Driveway and sidewalk work is underway on Sierra Ave, Bliss Ave., Rubidoux Ave., Lassen Ct., Sun Gold St., and Palm St. Parking restrictions apply. Retaining curb construction, landscaping reconnections and seeding and other clean-up activities will continue following driveway and sidewalk work for the next month.
Stage D: Crews continue ADA ramp improvements, landscaping reconnections and seeding, and other clean-up activities. Fire hydrant relocations may take place. ADA ramp improvements, and commercial driveway work on Palm Ave., Biskra St. and Indio Blvd. continues this week.
Week of January 9, 2023
JANUARY 12, 2023 | 9:50 p.m. Water service has been restored. Thank you for your patience.
JANUARY 12, 2023 | 5:20 p.m. | Crews are working to repair a damaged waterline on Tahquitz Ave. and Sun Gold St. Service will be restored soon.
Crews continue moving faster than anticipated, please expect accelerated timelines.
Construction in Stage A and B continue and crews have moved into Stage C ahead of schedule, and will return to the northern section of Stage D.
The Pedestrian Improvement Project is constructing new driveway approaches, sidewalks, adding crosswalks and updating ADA accessibility ramps to improve safety in your neighborhood.
Crews will work on one side then switch to the other side of a street once the initial side is complete. Crews continue with a leapfrog method to reduce inconvenience with resident access restrictions and improve overall efficiency to deliver a high-quality end-product for residents. Thank you for your continued patience.
ADA access accommodations are offered if necessary, please email the outreach team at info@HerbertHooverProject.com with your name, address, phone number, or call the hotline number above.
Work in your area
Stage A: Crews continue ADA ramp improvements, landscaping reconnection and seeding, and other clean-up activities. Driveway reconstruction and sidewalk construction are complete, however, retaining curb work, and fire hydrant relocations may take place. Work on Indio Blvd. is scheduled to begin January 9, 2023.
Stage B: Crews continue ADA ramp improvements, landscaping reconnection and seeding, and other clean-up activities. Driveway reconstruction and sidewalk construction are complete, however, retaining curb work, and fire hydrant relocations may take place. Work on Monroe St. is scheduled to begin January 9, 2023.
Stage C: Crews are working on water meter relocations, utility relocations, saw cutting work and other construction activities. Driveway and sidewalk work is underway on Sierra Ave, Bliss Ave., Rubidoux Ave., Lassen Ct., Sun Gold St., and Palm St. Parking restrictions apply. Retaining curb construction, landscaping reconnections and seeding and other clean-up activities will continue following driveway and sidewalk work for the next month.
Stage D: Crews continue ADA ramp improvements, landscaping reconnections and seeding, and other clean-up activities. Fire hydrant relocations may take place. ADA ramp improvements, and commercial driveway work on Palm Ave., Biskra St. and Indio Blvd. beginning January 9, 2023.
Week of January 3, 2023
HAPPY NEW YEAR! Crews are moving faster than anticipated, please expect accelerated timelines.
Construction in Stage A and B continue and crews have moved into Stage C ahead of schedule.
The Pedestrian Improvement Project is constructing new driveway approaches, sidewalks, adding crosswalks and updating ADA accessibility ramps to improve safety in your neighborhood.
Crews will work on one side then switch to the other side of a street once the initial side is complete. Crews continue with a leapfrog method to reduce inconvenience with resident access restrictions and improve overall efficiency to deliver a high-quality end-product for residents. Thank you for your continued patience.
ADA access accommodations are offered if necessary, please email the outreach team at info@HerbertHooverProject.com with your name, address, phone number, or call the hotline number above.
Work in your area
Stage A: Crews continue ADA ramp improvements, landscaping reconnection and seeding, and other clean-up activities. Driveway reconstruction and sidewalk construction are complete, however, retaining curb work, and fire hydrant relocations may take place. Work on Indio Blvd. is scheduled to begin the beginning of January.
Stage B: Crews continue different stages of driveway reconstruction and sidewalk construction on Rubidoux St. and Sun Gold St. Work on Monroe St. is scheduled to begin the beginning of January.
Stage C: Crews are working on water meter relocations, utility relocations, saw cutting work and other construction activities. Driveway and sidewalk work is underway on Sierra Ave, Bliss Ave., and Rubidoux Ave. Parking restrictions apply. Crews will begin construction activities on Lassen Ct., Sun Gold St., and Palm St.
Stage D: Crews continue ADA ramp improvements, landscaping reconnections and seeding, and other clean-up activities. Fire hydrant relocations may take place. ADA ramp improvements, and commercial driveway work on Palm Ave., Biskra St. and Indio Blvd. beginning in January.
Week of December 26, 2022
HAPPY HOLIDAYS! Crews are moving faster than anticipated, please expect accelerated timelines.
Construction in Stage A and B continue and crews have moved into Stage C ahead of schedule.
The Pedestrian Improvement Project is constructing new driveway approaches, sidewalks, adding crosswalks and updating ADA accessibility ramps to improve safety in your neighborhood.
Crews will work on one side then switch to the other side of a street once the initial side is complete. Crews continue with a leapfrog method to reduce inconvenience with resident access restrictions and improve overall efficiency to deliver a high-quality end-product for residents. Thank you for your continued patience.
ADA access accommodations are offered if necessary, please email the outreach team at info@HerbertHooverProject.com with your name, address, phone number, or call the hotline number above.
Work in your area
Stage A: Crews continue ADA ramp improvements, landscaping reconnection and seeding, and other clean-up activities. Driveway reconstruction and sidewalk construction are complete, however, retaining curb work, and fire hydrant relocations may take place. Work on Indio Blvd. is scheduled to begin the first week of January.
Stage B: Crews continue different stages of driveway reconstruction and sidewalk construction on Rubidoux St. and Sun Gold St. Work on Monroe St. is scheduled to begin the first week of January.
Stage C: Crews are working on water meter relocations, utility relocations, saw cutting work and other construction activities. Driveway and sidewalk work is underway on Sierra Ave, Bliss Ave., and Rubidoux Ave. Parking restrictions apply. Crews will begin construction activities on Lassen Ct., Sun Gold St., and Palm St.
Stage D: Crews continue ADA ramp improvements, landscaping reconnections and seeding, and other clean-up activities. Fire hydrant relocations may take place. ADA ramp improvements, and commercial driveway work on Palm Ave., Biskra St. and Indio Blvd are coming soon.
Week of December 19, 2022
Crews are moving faster than anticipated, please expect accelerated timelines.
Construction in Stage A and B continue and crews have moved into Stage C ahead of schedule.
The Pedestrian Improvement Project is constructing new driveway approaches, sidewalks, adding crosswalks and updating ADA accessibility ramps to improve safety in your neighborhood.
Crews will work on one side then switch to the other side of a street once the initial side is complete. Crews continue with a leapfrog method to reduce inconvenience and improve overall efficiency and deliver a high-quality end-product for residents.
ADA access accommodations are offered if necessary, please email the outreach team at info@HerbertHooverProject.com with your name, address, phone number, or call the hotline number above.
Work in your area
Stage A: Crews continue ADA ramp improvements, landscaping reconnection and seeding, and other clean-up activities. Driveway reconstruction and sidewalk construction are complete, however, retaining curb work, and fire hydrant relocations may take place. Work on Monroe St. and Indio Blvd. is coming soon.
Stage B: Crews continue driveway reconstruction and sidewalk construction on San Jacinto and Santa Rosa Avenues. Crews will then move to the west side of Rubidoux St., then next to Sun Gold St. between Miles and Tahquitz Avenues. Work on Monroe St. is planned to begin.
Stage C: Crews are working on water meter relocations, utility relocations, saw cutting work and other construction activities. Driveway and sidewalk work is underway. Parking restrictions apply.
Stage D: Crews continue ADA ramp improvements, landscaping reconnections and seeding, and other clean-up activities. Fire hydrant relocations may take place. Commercial driveway and outstanding work on Palm Ave., Biskra St. and Indio Blvd are coming soon.
Week of November 28, 2022
Crews are moving faster than anticipated, please expect accelerated timelines.
Construction in Stage A and B continue and crews will move into Stage C ahead of schedule.
The Pedestrian Improvement Project is constructing new driveway approaches, sidewalks, adding crosswalks and updating ADA accessibility ramps to improve safety in your neighborhood.
Crews will work on one side then switch to the other side of a street once the initial side is complete. Crews continue with a leapfrog method to reduce inconvenience and improve overall efficiency and a high-quality end-product for residents.
ADA access accommodations are offered if necessary, please email the outreach team at info@HerbertHooverProject.com with your name, address, phone number, or call the hotline number.
Work in your area
Stage A: Crews continue ADA ramp improvements, landscaping reconnection and seeding, and other clean-up activities. Driveway reconstruction and sidewalk construction are complete, however, retaining curb work may take place.
Stage B: Crews continue water meter relocations throughout the stage with driveway reconstruction and sidewalk construction on San Jacinto and Santa Rosa Avenues. Crews will then move to the west side of Rubidoux by Wednesday, Nov. 30 and next on Sun Gold Streets between Miles and Tahquitz Avenue.
Stage C: Crews will work on water meter relocations, utility relocations, and other pre-construction activities.
Stage D: Crews continue ADA ramp improvements, landscaping reconnections and seeding, and other clean-up activities.
Week of November 21, 2022
Crews are moving faster than anticipated, please expect accelerated timelines.
Construction in Stage A and B continue and crews will move into Stage C ahead of schedule.
The Pedestrian Improvement Project is constructing new driveway approaches, sidewalks, adding crosswalks and updating ADA accessibility ramps to improve safety in your neighborhood.
Crews will work on one side then switch to the other side of a street once the initial side is complete. Crews are using a leapfrog method with neighboring streets to reduce inconvenience and improve overall efficiency and produce a high-quality result for residents.
If ADA access accommodations are required at your address, please email our outreach team at info@HerbertHooverProject.com your name, address, and phone number, or call the hotline number.
Work in your area
Stage A: Crews continue ADA ramp improvements, landscaping reconnection and seeding, and other clean-up activities. In the southern section, water meter relocations continue along with driveway reconstruction and sidewalk construction.
Stage B: Crews continue water meter relocations throughout the stage with driveway reconstruction and sidewalk construction on San Jacinto Avenue.
Stage C: Crews will work on utility relocations and other preconstruction activities.
Stage D: Crews continue ADA ramp improvements, landscaping reconnections and seeding, and other clean-up activities.
Week of November 14, 2022: Construction moves forward into Stage B ahead of schedule. Crews are moving faster than anticipated, please expect accelerated timelines.
Different stages of driveway reconstruction and sidewalk construction continues in Stages D, A and B. Affected residents can expect large machinery, loud noises, and dust during working hours. Parking restrictions apply. Please click the Stage for locations.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Water meter relocations continue in multiple stages B and C. Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption. Please click the Stage for locations.
Note: Planned construction operations and posted schedules may change due to unforeseen field conditions.