Week of November 7, 2022

Construction moves into Stage B ahead of schedule. Crews are moving faster than anticipated, please expect accelerated timelines. 

Driveway reconstruction and sidewalk construction continues in Stages A and B. Affected residents can expect large machinery, loud noises, and dust during working hours. Parking restrictions apply. Please click the Stage for locations.

After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours. 

Water meter relocations continue in multiple stages A and B. Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption. Please click the Stage for locations.

Note: Planned construction operations and posted schedules may change due to unforeseen field conditions.

Week of October 31, 2022

Saw cutting, driveway excavation, driveway reconstruction, and sidewalk construction is planned in Stages A and B. Affected residents can expect large machinery, loud noises, and dust during working hours. Parking restrictions apply. Please click the Stage for locations.

After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours. 

Water meter relocations continue in multiple stages A and B. Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption. Please click the Stage for locations.

Note: Planned construction operations and posted schedules may change due to unforeseen field conditions.

Week of October 24, 2022

Saw cutting, driveway excavation, driveway reconstruction, and sidewalk construction is planned in Stages D and A. Affected residents can expect large machinery, loud noises, and dust during working hours. Parking restrictions apply. Please click the Stage for locations.

After NEW concrete is placed, residents may NOT walk on driveway or sidewalk for 24 hours and may NOT drive or park on driveway for 72 hours. 

Water meter relocations continue in multiple stages. Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption. Please click the Stage for locations.

Note: Planned construction operations and the posted schedule may change due to unforeseen field conditions.

Week of October 17, 2022

Saw cutting, driveway excavation, driveway reconstruction, and sidewalk construction is planned in Stages D and A. Affected residents can expect large machinery, loud noises, and dust during working hours. Parking restrictions apply. Please click the Stage for locations.

After new concrete is placed, residents may not walk on driveway or sidewalk for 24 hours and may not park on driveway for 72 hours. 

Water meter and fire hydrant relocations continue. Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption. Please click the Stage for locations.

Note: Planned construction operations and the posted schedule may change due to unforeseen field conditions.

Week of October 10, 2022

Crews continue removing large trees and stumps in all stages of the project area. The outreach and construction teams have notified or left flyers at affected residences. Please remove any plants that you would like to save within a 6-foot radius of pre-marked large trees and stumps.

Sawcutting, driveway excavation and reconstruction continue in Stages A and D. Sidewalk construction begins where driveways are complete. Affected residents can expect large machinery, loud noises and dust during working hours. 

After new concrete is placed, residents may not walk on driveway or sidewalk for 24 hours and may not park on driveway for 72 hours. 

Vegetation clearing, irrigation work, and utility potholing continue and are moving operations for Stages A and D. Please click the Stage for affected addresses and areas crews will be working. 

Note: Planned construction and posted schedules may change due to field conditions.*If you require ADA access accommodations, email info@HerbertHooverProject.com with brief description, name, address, and phone.

October 3, 2022

Crews will continue removing large trees in all stages of the project area. 

Stump removals continue. The outreach team has notified or left flyers at affected residences. Please remove any plants that you would like to save within a 6-foot radius of large trees and stumps that are marked.

Sawcutting, driveway excavation and driveway reconstruction is planned in Stages A and D. Affected residents can expect large machinery, loud noises and dust during working hours. 

Vegetation clearing is planned in planned for Stages A and D. Please click the Stage for addresses where crews will be working. 

Note: Planned construction operations and the posted schedule may change due to unforeseen field conditions.*If you require ADA access please send an email with a brief description, your name, address, and phone.

September 26, 2022

Crews will continue removing large trees in all stages of the project area. 

Stump removals will begin in Stages A and D. The outreach team has notified or left flyers at affected residences. Please remove any plants that you would like to save within a 6-foot radius of large trees and stumps that are marked.

Potholing, where crews cut holes in the ground/street to investigate what’s underground, will begin in Stage A. This is a moving operation, please watch for crews working in the street. 

Saw cutting, driveway excavation and driveway reconstruction is planned in Stages D and A. Affected residents can expect large machinery, loud noises and dust during working hours. 

Vegetation clearing is planned in planned for Stages D and A. Please click the Stage for addresses where crews will be working. 

Note: Planned construction operations and the posted schedule may change due to unforeseen field conditions.