Construction Update: Week of Feb. 6, 2023

LOCATION Luce Court None Monroe Street None Sun Gold Street None Tahquitz Avenue None Valencia Avenue None PLANNED WORK DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade,…

Read More

Construction Update: Week of January 30, 2023

LOCATION Luce Court None Monroe Street None Sun Gold Street Driveway, sidewalk, and retaining curb construction will continue. Irrigation relocation and repairs along with landscaping reseeding work will continue following driveway and sidewalk installations, ADA ramp work is scheduled. Tahquitz Avenue WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3…

Read More

Construction Update: Week of January 9, 2023

LOCATION Luce Court Outstanding curb and gutter work is tentatively scheduled in January. Monroe Street ADA ramp work on Monroe St. is scheduled to begin Jan. 9, 2023 and continue or 2-4 weeks. Sun Gold Street Driveway, sidewalk, and retaining curb construction will continue. Irrigation relocation and repairs along with landscaping reseeding work will occur…

Read More

Construction Update: Week of January 3, 2023

LOCATION Luce Court Outstanding curb and gutter work is tentatively scheduled in January. Monroe Street ADA ramp work on Monroe St. is scheduled to begin Jan. 5, 2023 and continue through late-January. Sun Gold Street ADA ramp work is scheduled soon. Tahquitz Avenue Outstanding driveway, sidewalk, and retaining curb construction will continue. Irrigation relocation and…

Read More

Construction Update: Week of Dec. 26, 2022

LOCATION Luce Court Outstanding curb and gutter work is tentatively scheduled in January. Monroe Street ADA ramp work on Monroe Street is scheduled to begin Jan. 5, 2023 and continue through late-January. Sun Gold Street ADA ramp work is scheduled soon. Tahquitz Avenue Outstanding driveway, sidewalk, and retaining curb construction will continue. Irrigation relocation and…

Read More

Construction Update: Week of Dec. 19, 2022

LOCATION Luce Court Outstanding tree work is tentatively scheduled for December 22. Monroe Street ADA ramp work on Monroe Street is scheduled for Tuesday, Dec. 20. Sun Gold Street None Tahquitz Avenue Crews continue to backfill, construct retaining curbs, along with other clean-up activities. Outstanding tree work is tentatively scheduled for December 22. Irrigation relocation…

Read More

Construction Update for week of Nov. 28, 2022

LOCATION Luce Court Irrigation relocation and repairs along with landscaping reseeding work will occur for the next month. Outstanding tree work is scheduled for mid-December. Monroe Street None Sun Gold Street None Tahquitz Avenue Crews continue to backfill, construct retaining curb, perform irrigation relocation/repairs including landscaping reseeding, along with other clean-up work. Outstanding tree work…

Read More

Construction Update week of Nov. 21, 2022

LOCATION Luce Court Irrigation relocation and repairs along with landscaping reseeding work will occur for the next month. Monroe Street None Sun Gold Street None Tahquitz Avenue Driveway and sidewalk construction activities continue in conjunction, working from Monroe Street to Sun Gold Street and from Rubidoux Street to Sun Gold Street. Irrigation relocation and repairs along…

Read More

Construction Update week of Nov. 14, 2022

LOCATION Water service disruption will occur in this stage the week of Nov. 14. Residents received a door hanger with the date of the planned disruption. Schedules may vary from flyer due to field conditions, crews will reach out. Luce Court Irrigation relocation and repairs along with landscaping reseeding work will occur for the next…

Read More