Stage B
Construction Update: Week of March 7, 2023
LOCATIONS Monroe Street None Rubidoux Street None San Jacinto Avenue None Santa Rosa Avenue None Sun Gold Street None PLANNED WORK: Crews have completed work in your area.
Read MoreConstruction Update: Week of Feb. 6, 2023
LOCATIONS Monroe Street None Rubidoux Street Retaining curb construction continues. Irrigation relocation and repairs along with landscaping reseeding work will continue following driveway and sidewalk installations. ADA ramp work is scheduled. San Jacinto Avenue Irrigation relocation and repairs along with landscaping reseeding work and retaining curb construction will continue following driveway and sidewalk installations. ADA…
Read MoreConstruction Update: Week of January 30, 2023
LOCATIONS Monroe Street None Rubidoux Street Retaining curb construction continues. Irrigation relocation and repairs along with landscaping reseeding work will continue following driveway and sidewalk installations. ADA ramp work is scheduled. San Jacinto Avenue Irrigation relocation and repairs along with landscaping reseeding work and retaining curb construction will continue following driveway and sidewalk installations. ADA…
Read MoreConstruction Update: Week of January 9, 2023
LOCATIONS Monroe Street ADA ramp work on Monroe Street and Santa Rosa Avenue is scheduled for Jan. 9, 2023 and will continue for 2-4 weeks. Rubidoux Street Retaining curb construction continues. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled. San…
Read MoreConstruction Update: Week of January 3, 2023
LOCATIONS Monroe Street ADA ramp work on Monroe Street and Santa Rosa Avenue is scheduled for Jan. 5, 2023 and will continue through late-January. Rubidoux Street Driveway, sidewalk, and retaining curb construction continues. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work…
Read MoreConstruction Update: Week of Dec. 26, 2022
LOCATIONS Monroe Street ADA ramp work on Monroe Street and Santa Rosa Avenue is scheduled for Jan. 5, 2023 and will continue through late-January. Rubidoux Street Driveway, sidewalk, and retaining curb construction continues. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work…
Read MoreConstruction Update: Week of Dec. 19, 2022
LOCATIONS Monroe Street ADA ramp work on Monroe Street and Santa Rosa Avenue is scheduled for Tuesday, Dec. 20. Rubidoux Street Driveway, sidewalk, and retaining curb construction will continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the next month. ADA ramp work will begin soon. WATER METER RELOCATIONS: Water service may…
Read MoreConstruction Update for week of Nov. 28, 2022
LOCATIONS Monroe Street None Rubidoux Street Driveway and sidewalk construction will begin by Wednesday, Nov. 30, water meter relocations continue. Water service disruption will occur on your street at the listed addresses the week of Nov. 28. The following residents received a door hanger with the date of the planned disruption: 44761, 44731, 44861, 44891…
Read MoreConstruction Update for week of Nov. 21, 2022
LOCATIONS Monroe Street None Rubidoux Street None San Jacinto Avenue Driveway and sidewalk construction continue from Monroe Street to Sun Gold Street and from Rubidoux Street to Sun Gold Street. Santa Rosa Avenue Pre-construction activities will resume with driveway and sidewalk construction coming soon. Water service disruption will occur on your street at the listed…
Read MoreConstruction Update for week of Nov. 21, 2022
LOCATIONS Monroe Street None Rubidoux Street None San Jacinto Avenue Driveway and sidewalk construction continues from Monroe Street to Sun Gold Street and from Sun Gold Street to Rubidoux Street. Santa Rosa Avenue Pre-construction activities will resume with driveway and sidewalk construction coming soon. Water service disruption will occur on your street at the listed…
Read More