Weekly Update

October 3, 2022

Crews will continue removing large trees in all stages of the project area. 

Stump removals will begin. The outreach team has notified or left flyers at affected residences. Please remove any plants that you would like to save within a 6-foot radius of large trees and stumps that are marked.

Sawcutting, driveway excavation and driveway reconstruction is planned in Stages A and D. Affected residents can expect large machinery, loud noises and dust during working hours. 

Vegetation clearing is planned in planned for Stages A and D. Please click the Stage for addresses where crews will be working. 

Note: Planned construction operations and the posted schedule may change due to unforeseen field conditions.*If you require ADA access please send an email with a brief description, your name, address, and phone.

Click on the map below for specific construction location & information.

Please click the STAGE (A, B, C or D) label in which you live on the map below for exact construction locations and additional information.

HH_legand
HH_legand Span

WORK HOURS:
Monday - Friday
6 a.m. to 6 p.m.

After Nov. 6, 2022
7 a.m. to 6 p.m.