Construction Update: Week of January 3, 2023
LOCATIONS
Bliss Avenue
Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.
Water meter relocations are scheduled and service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
1/3/23: 82105, 82139
Lassen Court
Driveway, sidewalk, and retaining curb construction will begin. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.
Miles Avenue
None
Monroe Street
ADA ramp work on Monroe St. is scheduled for Jan. 5, 2023 and will continue through late-January.
Palm Street
Driveway, sidewalk, and retaining curb construction will begin. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.
Rubidoux Street
Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.
Sierra Avenue
Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.
Sun Gold Street
Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.
PLANNED WORK
- Driveway construction
- Sidewalk construction
- Parking restrictions
- Limited pedestrian acces
- Utility relocation
- Pre-construction activities
- Water Meter relocations
- Fire hydrant relocations
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.