Construction Update: Week of Dec. 19, 2022
LOCATIONS
Expect crews to begin driveway and sidewalk construction before the year end.
Bliss Avenue
Construction activities including driveway, sidewalk, and retaining curb construction continues from Monroe Street to Sun Gold Street and from Rubidoux Street to Sun Gold Street.
Lassen Court
None
Miles Avenue
None
Monroe Street
ADA ramp work on Monroe Street is scheduled for Tuesday, Dec. 20.
Palm Street
None
Rubidoux Street
None
Sierra Avenue
Driveway, sidewalk, and retaining curb construction from Monroe Street to Sun Gold Street and from Rubidoux Street to Sun Gold Street continues.
WATER METER RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
12/21: 82289, 82291, 82269, 82259, 82251, 82245
12/22: 82235, 82227, 82217, 82211, 82153, 82137, 82055, 82053
Sun Gold Street
None
PLANNED WORK
- Driveway construction
- Sidewalk construction
- Parking restrictions
- Limited pedestrian acces
- Utility relocation
- Pre-construction activities
- Water Meter relocations
- Fire hydrant relocations
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.