Construction Update: Week of Dec. 19, 2022
LOCATIONS
Monroe Street
ADA ramp work on Monroe Street and Santa Rosa Avenue is scheduled for Tuesday, Dec. 20.
Rubidoux Street
Driveway, sidewalk, and retaining curb construction will continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the next month. ADA ramp work will begin soon.
WATER METER RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
12/19: 45290, 45280, 45260, 45240, 45210, 45170
12/20: 45140, 45120, 44980, 44962, 44948, 44924, 44800, 44778
12/21: 44758, 44730
San Jacinto Avenue
Driveway, sidewalk, and retaining curb construction continue from Monroe Street to Sun Gold Street and from Rubidoux Street to Sun Gold Street. Irrigation relocation and repairs along with landscaping reseeding work will occur for the next month.
Santa Rosa Avenue
Driveway, sidewalk, and retaining curb construction continue from Monroe Street to Sun Gold Street and from Rubidoux Street to Sun Gold Street. Irrigation relocation and repairs along with landscaping reseeding work will occur for the next month.
Sun Gold Street
Driveway, sidewalk, and retaining curb construction will continue. ADA ramp work will begin soon.
PLANNED WORK
- Driveway construction
- Sidewalk construction
- Water meter relocation
- Fire hydrant relocation
- Irrigation work
- ADA Ramp construction
- Parking restrictions
- Limited pedestrian acces
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.