Construction Update for week of Oct. 10, 2022
LOCATION
Arabia Street
None
Biskra Street:
44475, 44447, 44435, 44365, 44345, 44401, 44446, 444335 A1-2
Indio Boulevard
82475, 82431
Leroy Avenue:
None
Palm Street:
44320
Valencia Avenue:
82469, 82482, 82496, 82498, 82334, 82449, 82443, 82435
PLANNED WORK
The following construction activities are planned at the locations above.
- Driveway construction
- Sawcutting work
- Sidewalk construction begins where driveways are complete
- Utility potholing
- Mailbox relocations
- Vegetation removal
- Irrigation work
- Parking restrictions
- Limited pedestrian access
- Pre-construction activities
DRIVEWAY RECONSTRUCTION
During driveway reconstruction, residents may not drive on, or park in, the driveway for up to 12 days, which may only include one weekend.
After new concrete is placed, residents may not walk on driveway or sidewalk for 24 hours and park on the driveway for 72 hours.
Sawcutting work to prepare for driveway excavation and construction continues in Stages D and A. Affected residents can expect large machinery, loud noises, and dust during working hours.
VEGETATION REMOVAL
Vegetation clearing and stop removals continue. Please remove any plants or shrubs in the marked project area that you would like to save.