Construction Update for Sept. 26-30

LOCATION

Arabia Street
None

Biskra Street:
44475, 44447, 44435, 44365, 44345, 44401, 44446, 444335 A1-2

Indio Boulevard
82475, 82431

Leroy Avenue:
None

Palm Street:
44320 

Valencia Avenue:
82469, 82482, 82496, 82498, 82334, 82449, 82443, 82435

PLANNED WORK

The following construction activities are planned at the locations above. 

  • Driveway construction
  • Vegetation removal
  • Parking Restrictions
  • Limited Pedestrian Access
  • Pre-construction Activities

DRIVEWAY RECONSTRUCTION

During driveway reconstruction, residents may not drive on, or park in, the driveway for up to 12 days, which may only include one weekend. 

After new concrete is placed, residents may not park in the driveway for 72 hours. 

Saw cutting work to prepare for driveway excavation and construction continues in Stages D and A. Affected residents can expect large machinery, loud noises, and dust during working hours. 

VEGETATION REMOVAL

Vegetation clearing is planned in planned for Stage A. Please remove any plants or shrubs in the marked project that you would like to save. 