A: Construction Update week of Oct. 31, 2022
LOCATION
LOCATION
Luce Court
None
Monroe Street
None
Sun Gold Street
None
Tahquitz Avenue
Driveway and sidewalk construction activities continue from Sun Gold Street to Rubidoux Street.
Driveway demolition on the north side of the street from Monroe Street to Sun Gold Street.
Water service disruption will occur on your street at the listed addresses the week of Oct. 31. Schedules may vary from flyer due to field conditions. The following residents received a door hanger with the date of the planned disruption:
82012, 82054, 82060, 82076, 82092, 82138, 82154.
Valencia Avenue
Fire hydrant relocation coming soon.
The following construction activities are planned in this stage at or near the locations above.
PLANNED WORK
- ADA ramp construction
- Driveway construction
- Sidewalk construction begins where driveways are complete
- Water meter relocations
- Fire hydrant relocations
- Vegetation removal
- Irrigation work
- Parking restrictions, street parking permitted
- Limited pedestrian access
DRIVEWAY RECONSTRUCTION
During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction begins where driveways are complete.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
WATER METER & FIRE HYDRANT RELOCATIONS
Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instructions for the planned disruption.
VEGETATON REMOVAL
Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
POTHOLING
Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.