A: Construction Update week of Oct. 24, 2022
LOCATION
Luce Court
Driveway construction continues on the north side of street.
Water service disruption will occur on your street at the listed addresses through Oct. 28. Schedules may vary from flyer due to field conditions. The following residents received a door hanger with the date of the planned disruption:
82248, 82236
Monroe Street
None
Sun Gold Street
None
Tahquitz Avenue
Driveway construction continues on the south side of street, starting on the west end of the street near Monroe Street and moving towards the east end near Rubidoux Street.
Water service disruption will occur on your street at the listed addresses through Oct. 28. Schedules may vary from flyer due to field conditions. The following residents received a door hanger with the date of the planned disruption:
82013, 82025, 82039, 82055, 82061, 82077, 82093, 82109, 82123, 82139, 82153, 82205, 82211, 82217, 82233, 82249, 82265, 82281, 82297, 82311, 82325, 82335, 82339
Valencia Avenue
Driveway construction continues on the south side of street at the east end.
Water service disruption will occur on your street at the listed addresses through Oct. 28. Schedules may vary from flyer due to field conditions. The following residents received a door hanger with the date of the planned disruption:
82482
PLANNED WORK
- Sawcutting work
- Driveway construction
- Sidewalk construction begins where driveways are complete
- Water meter relocations
- Vegetation removal
- Irrigation work
- Mailbox relocations
- Parking restrictions, street parking permitted
- Limited pedestrian access
- Utility potholing
DRIVEWAY RECONSTRUCTION
During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction begins where driveways are complete.
After NEW concrete is placed, residents may NOT walk on driveway or sidewalk for 24 hours and may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
WATER METER & FIRE HYDRANT RELOCATIONS
Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instructions for the planned disruption.
VEGETATON REMOVAL
Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
POTHOLING
Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.