A: Construction Update week of Oct. 17, 2022

LOCATION

Luce Court
Driveway construction continues on the north side of street. 

Water service disruption will occur on your street at your address beginning Oct. 18 through Oct. 21. Schedules may vary from flyer due to file conditions. The following residents received a door hanger with the date of the planned disruption:

82248, 82236

Monroe Street
None

Sun Gold Street
None

Tahquitz Avenue

Driveway construction begins on the south side of street. Work will begin on the west end of the street near Monroe Street and move towards the east end near Rubidoux Street. 

Water service disruption will occur on your street at your address beginning Oct. 17 through Oct. 19. Schedules may vary from flyer due to file conditions. The following residents received a door hanger with the date of the planned disruption:

82013, 82025, 82039, 82055, 82061, 82077, 82093, 82109, 82123, 82139, 82153, 82205, 82211, 82217, 82233, 82249, 82265, 82281, 82297, 82311, 82325, 82335, 82339

Valencia Avenue
Driveway construction continues on the south side of street at the east end.

Water service disruption will occur on your street at your address beginning Oct. 18 through Oct. 21. Schedules may vary from flyer due to file conditions. The following residents received a door hanger with the date of the planned disruption:

82482

PLANNED WORK

  • Sawcutting work
  • Driveway construction 
  • Sidewalk construction begins where driveways are complete
  • Water meter relocations
  • Vegetation removal
  • Irrigation work
  • Mailbox relocations
  • Parking restrictions, street parking permitted
  • Limited pedestrian access
  • Utility potholing

DRIVEWAY RECONSTRUCTION

During driveway reconstruction residents may not drive on, or park in, the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, grade, form, and place concrete, this is a moving operation. Sidewalk construction begins where driveways are complete

After new concrete is placed, residents may not walk on driveway or sidewalk for 24 hours and may not park on driveway for 72 hours.

Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours. 

VEGETATON REMOVAL

Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save. 

POTHOLING

Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street. 

WATER METER & FIRE HYDRANT RELOCATIONS

Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.

TREE REMOVAL

Crews continue large tree and stump removals throughout the project area. The outreach team has left flyers at affected residences. Please remove any plants that you would like to save within a 6-foot radius of large trees and or stumps that are marked with bright orange dots or an x.