Construction Update for Oct. 3, 2022
LOCATION
Luce Court
82224, 82237, 82248, 82260, 82280, 82207,
82247, 82267, 82287, 88237, 822327, 82349
Monroe Street
None
Sun Gold Street
None
Tahquitz Avenue
82108, 82122, 82248
Valencia Avenue
82469
PLANNED WORK
- Sawcutting work
- Driveway construction
- Vegetation removal
- Irrigation work
- Mailbox relocations
- Parking restrictions
- Limited pedestrian access
- Pre-construction activities
DRIVEWAY RECONSTRUCTION
During driveway reconstruction, residents may not drive on, or park in, the driveway for up to 12 days, which may only include one weekend.
After new concrete is placed, residents may not park in the driveway for 72 hours.
Sawcutting work to prepare for driveway excavation and construction continues in Stages D and A. Affected residents can expect large machinery, loud noises, and dust during working hours.
VEGETATION REMOVAL
Vegetation clearing and stump removal continue. Please remove any plants or shrubs in the marked project area that you would like to save. Stump removals continue.