Stage A
Construction Update: Week of March 7, 2023
LOCATION
Luce Court
None
Monroe Street
None
Sun Gold Street
None
Tahquitz Avenue
None
Valencia Avenue
None
PLANNED WORK: Crews have completed work in your area.
Construction Update: Week of Feb. 6, 2023
LOCATION
Luce Court
None
Monroe Street
None
Sun Gold Street
None
Tahquitz Avenue
None
Valencia Avenue
None
PLANNED WORK
- ADA ramp construction
- Irrigation work
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instructions for the planned disruption.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
Construction Update: Week of January 30, 2023
LOCATION
Luce Court
None
Monroe Street
None
Sun Gold Street
Driveway, sidewalk, and retaining curb construction will continue. Irrigation relocation and repairs along with landscaping reseeding work will continue following driveway and sidewalk installations, ADA ramp work is scheduled.
Tahquitz Avenue
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption at the following addresses: 1/30/23 : 82248, 82264.
Valencia Avenue
None
PLANNED WORK
- Water meter relocations
- Driveway construction
- Sidewalk construction
- ADA ramp construction
- Fire hydrant relocations
- Irrigation work
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instructions for the planned disruption.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
Construction Update: Week of January 9, 2023
LOCATION
Luce Court
Outstanding curb and gutter work is tentatively scheduled in January.
Monroe Street
ADA ramp work on Monroe St. is scheduled to begin Jan. 9, 2023 and continue or 2-4 weeks.
Sun Gold Street
Driveway, sidewalk, and retaining curb construction will continue. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations, ADA ramp work is scheduled.
Tahquitz Avenue
Outstanding driveway, sidewalk, and retaining curb construction will continue. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.
Valencia Avenue
None
PLANNED WORK
- Driveway construction
- Sidewalk construction
- ADA ramp construction
- Fire hydrant relocations
- Irrigation work
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instructions for the planned disruption.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
Construction Update: Week of January 3, 2023
LOCATION
Luce Court
Outstanding curb and gutter work is tentatively scheduled in January.
Monroe Street
ADA ramp work on Monroe St. is scheduled to begin Jan. 5, 2023 and continue through late-January.
Sun Gold Street
ADA ramp work is scheduled soon.
Tahquitz Avenue
Outstanding driveway, sidewalk, and retaining curb construction will continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.
Valencia Avenue
None
PLANNED WORK
- ADA ramp construction
- Fire hydrant relocations
- Irrigation work
- Tree work
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instructions for the planned disruption.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
Construction Update: Week of Dec. 26, 2022
LOCATION
Luce Court
Outstanding curb and gutter work is tentatively scheduled in January.
Monroe Street
ADA ramp work on Monroe Street is scheduled to begin Jan. 5, 2023 and continue through late-January.
Sun Gold Street
ADA ramp work is scheduled soon.
Tahquitz Avenue
Outstanding driveway, sidewalk, and retaining curb construction will continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.
Valencia Avenue
None
PLANNED WORK
- ADA ramp construction
- Fire hydrant relocations
- Irrigation work
- Tree work
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instructions for the planned disruption.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
Construction Update: Week of Dec. 19, 2022
LOCATION
Luce Court
Outstanding tree work is tentatively scheduled for December 22.
Monroe Street
ADA ramp work on Monroe Street is scheduled for Tuesday, Dec. 20.
Sun Gold Street
None
Tahquitz Avenue
Crews continue to backfill, construct retaining curbs, along with other clean-up activities. Outstanding tree work is tentatively scheduled for December 22. Irrigation relocation and repairs along with landscape reseeding work will occur for the next month.
Valencia Avenue
None
PLANNED WORK
- ADA ramp construction
- Fire hydrant relocations
- Irrigation work
- Tree work
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instructions for the planned disruption.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
Construction Update for week of Nov. 28, 2022
LOCATION
Luce Court
Irrigation relocation and repairs along with landscaping reseeding work will occur for the next month. Outstanding tree work is scheduled for mid-December.
Monroe Street
None
Sun Gold Street
None
Tahquitz Avenue
Crews continue to backfill, construct retaining curb, perform irrigation relocation/repairs including landscaping reseeding, along with other clean-up work. Outstanding tree work is scheduled for mid-December.
Valencia Avenue
None
PLANNED WORK
- ADA ramp construction
- Fire hydrant relocations
- Irrigation work
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instructions for the planned disruption.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
Construction Update week of Nov. 21, 2022
LOCATION
Luce Court
Irrigation relocation and repairs along with landscaping reseeding work will occur for the next month.
Monroe Street
None
Sun Gold Street
None
Tahquitz Avenue
Driveway and sidewalk construction activities continue in conjunction, working from Monroe Street to Sun Gold Street and from Rubidoux Street to Sun Gold Street. Irrigation relocation and repairs along with landscaping reseeding, and other clean-up work will occur for the next month.
Valencia Avenue
Fire hydrant relocation coming soon.
PLANNED WORK
- ADA ramp construction
- Driveway construction
- Sidewalk construction
- Water meter relocations
- Fire hydrant relocations
- Vegetation removal
- Irrigation work
- Parking restrictions, street parking permitted
- Limited pedestrian access
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instructions for the planned disruption.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
Construction Update week of Nov. 14, 2022
LOCATION
Water service disruption will occur in this stage the week of Nov. 14. Residents received a door hanger with the date of the planned disruption. Schedules may vary from flyer due to field conditions, crews will reach out.
Luce Court
Irrigation relocation and repairs along with landscaping reseeding work will occur for the next few weeks.
Monroe Street
None
Sun Gold Street
None
Tahquitz Avenue
Driveway and sidewalk construction activities continues in conjunction working east towards Rubidoux Street. Water service disruption will be completed on your street by the week of Nov. 14. .
Valencia Avenue
Fire hydrant relocation coming soon.
PLANNED WORK
- ADA ramp construction
- Driveway construction
- Sidewalk construction
- Water meter relocations
- Fire hydrant relocations
- Vegetation removal
- Irrigation work
- Parking restrictions, street parking permitted
- Limited pedestrian access
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction begins where driveways are complete.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instructions for the planned disruption.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
Click on the map below for specific construction location & information.
Please click the STAGE (A, B, C or D) label in which you live on the map below for exact construction locations and additional information.


WORK HOURS:
Monday - Friday
7 a.m. to 6 p.m.