Stage B

Construction Update: Week of March 7, 2023

LOCATIONS

Monroe Street

None

Rubidoux Street

None

San Jacinto Avenue

None

Santa Rosa Avenue

None

Sun Gold Street

None

PLANNED WORK: Crews have completed work in your area.

Construction Update: Week of Feb. 6, 2023

LOCATIONS

Monroe Street

None

Rubidoux Street

Retaining curb construction continues. Irrigation relocation and repairs along with landscaping reseeding work will continue following driveway and sidewalk installations. ADA ramp work is scheduled.

San Jacinto Avenue

Irrigation relocation and repairs along with landscaping reseeding work and retaining curb construction will continue following driveway and sidewalk installations. ADA ramp work is scheduled.

Santa Rosa Avenue

Irrigation relocation and repairs along with landscaping reseeding work and retaining curb construction will continue following driveway and sidewalk installations. ADA ramp work is scheduled.

Sun Gold Street

Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will continue following driveway and sidewalk installations. ADA ramp work is scheduled.

PLANNED WORK

  • Irrigation work
  • ADA Ramp construction

DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.

Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours. 

After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours. 

WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.

VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save. 

Construction Update: Week of January 30, 2023

LOCATIONS

Monroe Street

None

Rubidoux Street

Retaining curb construction continues. Irrigation relocation and repairs along with landscaping reseeding work will continue following driveway and sidewalk installations. ADA ramp work is scheduled.

San Jacinto Avenue

Irrigation relocation and repairs along with landscaping reseeding work and retaining curb construction will continue following driveway and sidewalk installations. ADA ramp work is scheduled.

Santa Rosa Avenue

Irrigation relocation and repairs along with landscaping reseeding work and retaining curb construction will continue following driveway and sidewalk installations. ADA ramp work is scheduled.

Sun Gold Street

Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will continue following driveway and sidewalk installations. ADA ramp work is scheduled.

PLANNED WORK

  • Driveway construction
  • Sidewalk construction
  • Water meter relocation
  • Fire hydrant relocation
  • Irrigation work
  • ADA Ramp construction
  • Parking restrictions
  • Limited pedestrian acces

DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.

Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours. 

After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours. 

WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.

VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save. 

Construction Update: Week of January 9, 2023

LOCATIONS

Monroe Street

ADA ramp work on Monroe Street and Santa Rosa Avenue is scheduled for Jan. 9, 2023 and will continue for 2-4 weeks.

Rubidoux Street

Retaining curb construction continues. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled.

San Jacinto Avenue

Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled.

Santa Rosa Avenue

Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled.

Sun Gold Street

Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled.

PLANNED WORK

  • Driveway construction
  • Sidewalk construction
  • Water meter relocation
  • Fire hydrant relocation
  • Irrigation work
  • ADA Ramp construction
  • Parking restrictions
  • Limited pedestrian acces

DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.

Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours. 

After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours. 

WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.

VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save. 

Construction Update: Week of January 3, 2023

LOCATIONS

Monroe Street

ADA ramp work on Monroe Street and Santa Rosa Avenue is scheduled for Jan. 5, 2023 and will continue through late-January.

Rubidoux Street

Driveway, sidewalk, and retaining curb construction continues. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.

San Jacinto Avenue

Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.

Santa Rosa Avenue

Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.

Sun Gold Street

Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.

PLANNED WORK

  • Driveway construction
  • Sidewalk construction
  • Water meter relocation
  • Fire hydrant relocation
  • Irrigation work
  • ADA Ramp construction
  • Parking restrictions
  • Limited pedestrian acces

WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.

DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.

After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours. 

Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours. 

VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save. 

Construction Update: Week of Dec. 26, 2022

LOCATIONS

Monroe Street

ADA ramp work on Monroe Street and Santa Rosa Avenue is scheduled for Jan. 5, 2023 and will continue through late-January.

Rubidoux Street

Driveway, sidewalk, and retaining curb construction continues. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.

San Jacinto Avenue

Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.

Santa Rosa Avenue

Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.

Sun Gold Street

Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.

PLANNED WORK

  • Driveway construction
  • Sidewalk construction
  • Water meter relocation
  • Fire hydrant relocation
  • Irrigation work
  • ADA Ramp construction
  • Parking restrictions
  • Limited pedestrian acces

WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.

DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.

After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours. 

Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours. 

VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save. 

Construction Update: Week of Dec. 19, 2022

LOCATIONS

Monroe Street

ADA ramp work on Monroe Street and Santa Rosa Avenue is scheduled for Tuesday, Dec. 20.

Rubidoux Street

Driveway, sidewalk, and retaining curb construction will continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the next month. ADA ramp work will begin soon.

WATER METER RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.

12/19: 45290, 45280, 45260, 45240, 45210, 45170

12/20: 45140, 45120, 44980, 44962, 44948, 44924, 44800, 44778

12/21: 44758, 44730

San Jacinto Avenue

Driveway, sidewalk, and retaining curb construction continue from Monroe Street to Sun Gold Street and from Rubidoux Street to Sun Gold Street. Irrigation relocation and repairs along with landscaping reseeding work will occur for the next month.

Santa Rosa Avenue

Driveway, sidewalk, and retaining curb construction continue from Monroe Street to Sun Gold Street and from Rubidoux Street to Sun Gold Street. Irrigation relocation and repairs along with landscaping reseeding work will occur for the next month.

Sun Gold Street

Driveway, sidewalk, and retaining curb construction will continue. ADA ramp work will begin soon.

PLANNED WORK

  • Driveway construction
  • Sidewalk construction
  • Water meter relocation
  • Fire hydrant relocation
  • Irrigation work
  • ADA Ramp construction
  • Parking restrictions
  • Limited pedestrian acces

WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.

DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.

After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours. 

Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours. 

VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save. 

Construction Update for week of Nov. 28, 2022

LOCATIONS

Monroe Street

None

Rubidoux Street

Driveway and sidewalk construction will begin by Wednesday, Nov. 30, water meter relocations continue.

Water service disruption will occur on your street at the listed addresses the week of Nov. 28. The following residents received a door hanger with the date of the planned disruption:

44761, 44731, 44861, 44891

San Jacinto Avenue

Driveway and sidewalk construction continue from Monroe Street to Sun Gold Street and from Rubidoux Street to Sun Gold Street.

Santa Rosa Avenue

Driveway and sidewalk construction continue from Monroe Street to Sun Gold Street and from Rubidoux Street to Sun Gold Street.

Sun Gold Street

Driveway and sidewalk construction coming soon, water meter relocations continue.

PLANNED WORK

  • Driveway construction
  • Sidewalk construction
  • Water meter relocation
  • Fire hydrant relocation
  • Irrigation work
  • ADA Ramp construction
  • Parking restrictions
  • Limited pedestrian acces

WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.

DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.

After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours. 

Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours. 

VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save. 

Construction Update for week of Nov. 21, 2022

LOCATIONS

Monroe Street

None

Rubidoux Street

None

San Jacinto Avenue

Driveway and sidewalk construction continue from Monroe Street to Sun Gold Street and from Rubidoux Street to Sun Gold Street.

Santa Rosa Avenue

Pre-construction activities will resume with driveway and sidewalk construction coming soon.

Water service disruption will occur on your street at the listed addresses the week of Nov. 21. The following residents received a door hanger with the date of the planned disruption:

82265, 82281, 82139, 82123, 82109, 82093, 82055, 82039

Sun Gold Street

None

PLANNED WORK

  • Driveway construction
  • Sidewalk construction
  • Water meter relocation
  • Irrigation work
  • Parking restrictions
  • Utility potholing
  • Limited pedestrian acces

WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.

DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.

After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours. 

Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours. 

VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save. 

POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street. 

Construction Update for week of Nov. 21, 2022

LOCATIONS

Monroe Street

None

Rubidoux Street

None

San Jacinto Avenue

Driveway and sidewalk construction continues from Monroe Street to Sun Gold Street and from Sun Gold Street to Rubidoux Street.

Santa Rosa Avenue

Pre-construction activities will resume with driveway and sidewalk construction coming soon.

Water service disruption will occur on your street at the listed addresses the week of Nov. 21. The following residents received a door hanger with the date of the planned disruption:

82265, 82281, 82139, 82123, 82109, 82093, 82055, 82039

Sun Gold Street

None

PLANNED WORK

  • Driveway construction
  • Sidewalk construction
  • Water meter relocation
  • Irrigation work
  • Parking restrictions
  • Utility potholing
  • Limited pedestrian acces

WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.

DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction begins where driveways are complete.

After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours ,if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours. 

Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours. 

VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save. 

POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street. 

Click on the map below for specific construction location & information.

Please click the STAGE (A, B, C or D) label in which you live on the map below for exact construction locations and additional information.