Stage C
Construction Update: Week of March 7, 2023
LOCATIONS
Bliss Avenue
None
Lassen Court
None
Miles Avenue
None
Monroe Street
None
Palm Street
None
Rubidoux Street
None
Sierra Avenue
None
Sun Gold Street
None
PLANNED WORK: Crews have completed work in your area.
Construction Update: Week of Feb. 6, 2023
LOCATIONS
Bliss Avenue
Retaining curb construction continues. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled.
Lassen Court
Retaining curb construction continues. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled.
Miles Avenue
None
Monroe Street
None
Palm Street
Retaining curb construction continues. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled.
Rubidoux Street
Retaining curb construction continues. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled.
Sierra Avenue
Retaining curb construction continues. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled.
Sun Gold Street
Retaining curb construction continues. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled.
PLANNED WORK
- ADA Ramp construction
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
Construction Update: Week of January 30, 2023
LOCATIONS
Bliss Avenue
Retaining curb construction continues. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled.
Lassen Court
Driveway, sidewalk, and retaining curb construction continues. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled.
Miles Avenue
None
Monroe Street
None
Palm Street
Driveway, sidewalk, and retaining curb construction continues. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled.
Rubidoux Street
Retaining curb construction continues. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled.
Sierra Avenue
Driveway, sidewalk, and retaining curb construction continues. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.
Sun Gold Street
Driveway, sidewalk, and retaining curb construction continues. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled.
PLANNED WORK
- Driveway construction
- Sidewalk construction
- Parking restrictions
- Limited pedestrian acces
- ADA Ramp construction
- Utility relocation
- Pre-construction activities
- Water Meter relocations
- Fire hydrant relocations
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
Construction Update: Week of January 9, 2023
LOCATIONS
Bliss Avenue
Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled.
Lassen Court
Driveway, sidewalk, and retaining curb construction begins. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled.
Miles Avenue
ADA ramp work is scheduled.
Monroe Street
ADA ramp work on Monroe St. is scheduled for Jan. 9, 2023 and will continue for 2-4 weeks.
Palm Street
Driveway, sidewalk, and retaining curb construction begins. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled.
Rubidoux Street
Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled.
Sierra Avenue
Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.
Sun Gold Street
Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled.
PLANNED WORK
- Driveway construction
- Sidewalk construction
- Parking restrictions
- Limited pedestrian acces
- ADA Ramp construction
- Utility relocation
- Pre-construction activities
- Water Meter relocations
- Fire hydrant relocations
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
Construction Update: Week of January 3, 2023
LOCATIONS
Bliss Avenue
Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.
Water meter relocations are scheduled and service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
1/3/23: 82105, 82139
Lassen Court
Driveway, sidewalk, and retaining curb construction will begin. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.
Miles Avenue
None
Monroe Street
ADA ramp work on Monroe St. is scheduled for Jan. 5, 2023 and will continue through late-January.
Palm Street
Driveway, sidewalk, and retaining curb construction will begin. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.
Rubidoux Street
Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.
Sierra Avenue
Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.
Sun Gold Street
Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.
PLANNED WORK
- Driveway construction
- Sidewalk construction
- Parking restrictions
- Limited pedestrian acces
- Utility relocation
- Pre-construction activities
- Water Meter relocations
- Fire hydrant relocations
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
Construction Update: Week of Dec. 26, 2022
LOCATIONS
Bliss Avenue
Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.
Lassen Court
Driveway, sidewalk, and retaining curb construction will begin. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.
Miles Avenue
None
Monroe Street
ADA ramp work on Monroe Street is scheduled for Jan. 5, 2023 and will continue through late-January.
Palm Street
Driveway, sidewalk, and retaining curb construction will begin. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon. Water meter relocations are scheduled and service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
Rubidoux Street
Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.
Sierra Avenue
Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.
Sun Gold Street
Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur for the month following driveway and sidewalk installations. ADA ramp work is scheduled soon.
PLANNED WORK
- Driveway construction
- Sidewalk construction
- Parking restrictions
- Limited pedestrian acces
- Utility relocation
- Pre-construction activities
- Water Meter relocations
- Fire hydrant relocations
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
Construction Update: Week of Dec. 19, 2022
LOCATIONS
Expect crews to begin driveway and sidewalk construction before the year end.
Bliss Avenue
Construction activities including driveway, sidewalk, and retaining curb construction continues from Monroe Street to Sun Gold Street and from Rubidoux Street to Sun Gold Street.
Lassen Court
None
Miles Avenue
None
Monroe Street
ADA ramp work on Monroe Street is scheduled for Tuesday, Dec. 20.
Palm Street
None
Rubidoux Street
None
Sierra Avenue
Driveway, sidewalk, and retaining curb construction from Monroe Street to Sun Gold Street and from Rubidoux Street to Sun Gold Street continues.
WATER METER RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
12/21: 82289, 82291, 82269, 82259, 82251, 82245
12/22: 82235, 82227, 82217, 82211, 82153, 82137, 82055, 82053
Sun Gold Street
None
PLANNED WORK
- Driveway construction
- Sidewalk construction
- Parking restrictions
- Limited pedestrian acces
- Utility relocation
- Pre-construction activities
- Water Meter relocations
- Fire hydrant relocations
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
Construction Update for week of Nov. 28, 2022
LOCATIONS
Fire Hydrant and water meter relocations continue throughout.
Bliss Avenue
None
Lassen Court
None
Miles Avenue
None
Monroe Street
None
Palm Street
None
Rubidoux Street
None
Sierra Avenue
None
Sun Gold Street
None
PLANNED WORK
- Utility relocation
- Pre-construction activities
- Water Meter relocations
- Fire hydrant relocations
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
Construction Update for week of Nov. 21, 2022
LOCATIONS
Bliss Avenue
None
Lassen Court
Street light relocation coming soon.
Miles Avenue
None
Monroe Street
None
Palm Street
None
Rubidoux Street
None
Sierra Avenue
Street light relocation coming soon.
Sun Gold Street
None
PLANNED WORK
- Utility relocation
- Pre-construction activities
- Water Meter relocations
- Fire hydrant relocations
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
Construction Update for week of Nov. 14, 2022
LOCATIONS
Water service disruption will occur in this stage the week of Nov. 14. Residents received a door hanger with the date of the planned disruption. Schedules may vary from flyer due to field conditions, crews will reach out.
Bliss Avenue
None
Lassen Court
Street light relocation coming soon.
Miles Avenue
None
Monroe Street
None
Palm Street
None
Rubidoux Street
None
Sierra Avenue
Street light relocation coming soon.
Sun Gold Street
None
PLANNED WORK
- Utility relocation
- Pre-construction activities
- Water Meter relocations
- Fire hydrant relocations
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction begins where driveways are complete.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
Click on the map below for specific construction location & information.
Please click the STAGE (A, B, C or D) label in which you live on the map below for exact construction locations and additional information.


WORK HOURS:
Monday - Friday
7 a.m. to 6 p.m.