Stage D
Construction Update: Week of March 7, 2023
LOCATION
Arabia Street
None
Biskra Street
None
Indio Boulevard
None
Leroy Avenue
None
Palm Street
None
Valencia Avenue
None
PLANNED WORK: Crews have completed work in your area.
Construction Update: Week of Feb. 6, 2023
LOCATION
Arabia Street
None
Biskra Street
None
Indio Boulevard
None
Leroy Avenue
None
Palm Street
None
Valencia Avenue
None
PLANNED WORK
- Remaining punch list construction activities
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
Construction Update: Week of January 30, 2023
LOCATION
Arabia Street
None
Biskra Street
None
Indio Boulevard
None
Leroy Avenue
None
Palm Street
None
Valencia Avenue
None
PLANNED WORK
- Driveway construction
- Sidewalk construction
- ADA ramp construction
- Irrigation work
- Water meter relocation
- Fire hydrant relocation
- Remaining construction activities
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
Construction Update: Week of January 9, 2023
LOCATION
Arabia Street
Watch for crews working near Indio Blvd.
Biskra Street
Driveway, sidewalk, and retaining curb construction continue. Irrigation relocation and repairs along with landscaping reseeding work will occur the month following driveway and sidewalk installations. ADA ramp work is scheduled. Watch for crews working near Indio Blvd.
Indio Boulevard
ADA ramp work and commercial driveway work on Indio Blvd. is scheduled for Jan. 9, 2023 and will continue for 2-4 weeks.
Leroy Avenue
None
Palm Street
Watch for crews working near Indio Blvd.
Valencia Avenue
None
PLANNED WORK
- Driveway construction
- Sidewalk construction
- ADA ramp construction
- Irrigation work
- Water meter relocation
- Fire hydrant relocation
- Remaining construction activities
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
Construction Update: Week of January 3, 2023
LOCATION
Arabia Street
None
Biskra Street
None
Indio Boulevard
ADA ramp work and Commercial driveway work on Indio Blvd. is scheduled for Jan. 5, 2023 and will continue through late-January.
Leroy Avenue
None
Palm Street
None
Valencia Avenue
None
PLANNED WORK
- ADA ramp construction
- Irrigation work
- Water meter relocation
- Fire hydrant relocation
- Remaining construction activities
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
Construction Update: Week of Dec. 26, 2022
LOCATION
Arabia Street
None
Biskra Street
None
Indio Boulevard
ADA ramp work and Commercial driveway work on Indio Blvd. is scheduled for Jan.5, 2023 and will continue through late-January.
Leroy Avenue
None
Palm Street
None
Valencia Avenue
None
PLANNED WORK
- ADA ramp construction
- Irrigation work
- Water meter relocation
- Fire hydrant relocation
- Remaining construction activities
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
Construction Update: Week of Dec. 19, 2022
LOCATION
ADA ramp installations continue throughout.
Arabia Street
None
Biskra Street
Remaining construction activities will take place soon.
Indio Boulevard
Commercial driveway construction coming soon.
Leroy Avenue
None
Palm Street
Remaining construction activities will take place soon.
Valencia Avenue
None
PLANNED WORK
- ADA ramp construction
- Irrigation work
- Water meter relocation
- Fire hydrant relocation
- Remaining construction activities
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
Construction Update for week of Nov. 28, 2022
LOCATION
ADA ramp installations continue throughout.
Arabia Street
None
Biskra Street
None
Indio Boulevard
Commercial driveway construction coming soon.
Leroy Avenue
None
Palm Street
None
Valencia Avenue
None
PLANNED WORK
- ADA ramp construction
- Irrigation work
- Water meter relocation
- Fire hydrant relocation
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
Construction Update for week of Nov. 21, 2022
LOCATION
Arabia Street
None
Biskra Street
None
Indio Boulevard
Commercial driveway construction coming soon.
Leroy Avenue
None
Palm Street
None
Valencia Avenue
ADA ramp installations continue.
PLANNED WORK
- ADA ramp construction
- Driveway reconstruction
- Sidewalk construction
- Irrigation work
- Water meter relocation
- Fire hydrant relocation
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction will occur in conjunction with driveway work.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
Construction Update for week of Nov. 14, 2022
LOCATION
Water service disruption will occur in this stage the week of Nov. 14. Residents received a door hanger with the date of the planned disruption. Schedules may vary from flyer due to field conditions, crews will reach out.
Arabia Street
None
Biskra Street
None
Indio Boulevard
Commercial driveway construction coming soon.
Leroy Avenue
None
Palm Street
None
Valencia Avenue
ADA ramp installations continue.
PLANNED WORK
- ADA ramp construction
- Driveway reconstruction
- Sidewalk construction
- Irrigation work
- Water meter relocation
- Fire hydrant relocation
DRIVEWAY RECONSTRUCTION: During driveway reconstruction residents may not drive on, or park in the driveway for up to 12 days, which may only include one weekend. PLEASE PARK ACROSS THE STREET. Crews will demolish, excavate, grade, form, place concrete, cure, remove forms, and then backfill, this is a moving operation. Sidewalk construction begins where driveways are complete.
After NEW concrete is placed, residents may walk on driveways or sidewalks after 4 hours, if necessary, but waiting 24 hours is recommended. Residents may NOT drive or park on driveway for 72 hours.
Saw cutting work prepares for driveway demolition, excavation, and reconstruction. Affected residents can expect large machinery, loud noises and dust during working hours.
WATER METER & FIRE HYDRANT RELOCATIONS: Water service may be disrupted for up to 3 – 5 hours once your water is shut off. Residents will receive a door hanger with the date and instruction for the planned disruption.
VEGETATION REMOVAL: Vegetation clearing continues. Please remove any plants or shrubs in the marked project area that you would like to save.
POTHOLING: Potholing, where crews cut holes in the ground/street to investigate what’s underground. This is a moving operation, please watch for crews working in the street.
Click on the map below for specific construction location & information.
Please click the STAGE (A, B, C or D) label in which you live on the map below for exact construction locations and additional information.


WORK HOURS:
Monday - Friday
7 a.m. to 6 p.m.