Week of January 9, 2023
JANUARY 12, 2023 | 9:50 p.m. Water service has been restored. Thank you for your patience.
JANUARY 12, 2023 | 5:20 p.m. | Crews are working to repair a damaged waterline on Tahquitz Ave. and Sun Gold St. Service will be restored soon.
Crews continue moving faster than anticipated, please expect accelerated timelines.
Construction in Stage A and B continue and crews have moved into Stage C ahead of schedule, and will return to the northern section of Stage D.
The Pedestrian Improvement Project is constructing new driveway approaches, sidewalks, adding crosswalks and updating ADA accessibility ramps to improve safety in your neighborhood.
Crews will work on one side then switch to the other side of a street once the initial side is complete. Crews continue with a leapfrog method to reduce inconvenience with resident access restrictions and improve overall efficiency to deliver a high-quality end-product for residents. Thank you for your continued patience.
ADA access accommodations are offered if necessary, please email the outreach team at info@HerbertHooverProject.com with your name, address, phone number, or call the hotline number above.
Work in your area
Stage A: Crews continue ADA ramp improvements, landscaping reconnection and seeding, and other clean-up activities. Driveway reconstruction and sidewalk construction are complete, however, retaining curb work, and fire hydrant relocations may take place. Work on Indio Blvd. is scheduled to begin January 9, 2023.
Stage B: Crews continue ADA ramp improvements, landscaping reconnection and seeding, and other clean-up activities. Driveway reconstruction and sidewalk construction are complete, however, retaining curb work, and fire hydrant relocations may take place. Work on Monroe St. is scheduled to begin January 9, 2023.
Stage C: Crews are working on water meter relocations, utility relocations, saw cutting work and other construction activities. Driveway and sidewalk work is underway on Sierra Ave, Bliss Ave., Rubidoux Ave., Lassen Ct., Sun Gold St., and Palm St. Parking restrictions apply. Retaining curb construction, landscaping reconnections and seeding and other clean-up activities will continue following driveway and sidewalk work for the next month.
Stage D: Crews continue ADA ramp improvements, landscaping reconnections and seeding, and other clean-up activities. Fire hydrant relocations may take place. ADA ramp improvements, and commercial driveway work on Palm Ave., Biskra St. and Indio Blvd. beginning January 9, 2023.