Week of November 28, 2022

Crews are moving faster than anticipated, please expect accelerated timelines. 

Construction in Stage A and B continue and crews will move into Stage C ahead of schedule.

The Pedestrian Improvement Project is constructing new driveway approaches, sidewalks, adding crosswalks and updating ADA accessibility ramps to improve safety in your neighborhood. 

Crews will work on one side then switch to the other side of a street once the initial side is complete. Crews continue with a leapfrog method to reduce inconvenience and improve overall efficiency and a high-quality end-product for residents. 

ADA access accommodations are offered if necessary, please email the outreach team at info@HerbertHooverProject.com with your name, address, phone number, or call the hotline number.

Work in your area

Stage A: Crews continue ADA ramp improvements, landscaping reconnection and seeding, and other clean-up activities. Driveway reconstruction and sidewalk construction are complete, however, retaining curb work may take place.

Stage B: Crews continue water meter relocations throughout the stage with driveway reconstruction and sidewalk construction on San Jacinto and Santa Rosa Avenues. Crews will then move to the west side of Rubidoux by Wednesday, Nov. 30 and next on Sun Gold Streets between Miles and Tahquitz Avenue.

Stage C: Crews will work on water meter relocations, utility relocations, and other pre-construction activities.

Stage D: Crews continue ADA ramp improvements, landscaping reconnections and seeding, and other clean-up activities. 