September 26, 2022

Crews will continue removing large trees in all stages of the project area. 

Stump removals will begin in Stages A and D. The outreach team has notified or left flyers at affected residences. Please remove any plants that you would like to save within a 6-foot radius of large trees and stumps that are marked.

Potholing, where crews cut holes in the ground/street to investigate what’s underground, will begin in Stage A. This is a moving operation, please watch for crews working in the street. 

Saw cutting, driveway excavation and driveway reconstruction is planned in Stages D and A. Affected residents can expect large machinery, loud noises and dust during working hours. 

Vegetation clearing is planned in planned for Stages D and A. Please click the Stage for addresses where crews will be working. 

Note: Planned construction operations and the posted schedule may change due to unforeseen field conditions.